Inspections

To schedule an inspection:

Login to your Online Permit to schedule, by clicking here.

Call Building Inspector Andrew Mentelle 605-280-8389.

Inspection Requests

It shall be the duty of the permit holder or their agent to notify the building official 24 hours in advance that such work is ready for inspection.  It shall be the duty of the person requesting any inspection required by this code to provide access and means for inspection of such work.  Any inspections that are completed on a legal holiday will be assessed a fee.

Approval Requirements

Work shall not be done beyond the point indicated in each successive inspection without first obtaining approval of the building official.  The building official, upon notification, shall make the requested inspection and shall either indicate the portion of the construction that is satisfactory as completed, or shall notify the permit holder or an agent of the permit holder wherein the same fails to comply with this code.  Any portions that do not comply shall be corrected and such portion shall not be covered or concealed until authorized by the building official

  1. Setbacks
  2. Footing 
  3. Foundation Wall 
  4. Interior Concrete Slab
  5. Framing 
  6. Mechanical & Gas
  7. Drywall / Sheetrock
  8. Final

Prior to setting form for foundation/basement walls.  Please mark out location of walls forms on the footings. A lot survey may be required by the building official to verify that the structure is located in accordance with the approved plans.